Measure:
Renewal of drinking water pipelines
Streets:
Bodelschwinghstraße - from the junction with Johannisstraße to the end of Bodelschwinghstraße
Executed by construction company:
HTB Baugesellschaft mbH
Restriction:
Partial road closure with no parking on both sides in the construction area
Period:
23.03.2026 expected until 21.08.2026
Measure:
Installation of a protective scaffold with safety net over the roadway - overhead line construction
Streets:
L 128 Hauptstraße - outside the town
Executed by construction company:
E.E.R. Harald Lück
Restriction:
Temporary speed reduction
Period:
10.05.2026 expected until 30.08.2026
Measure:
Installation of a construction scaffold
Streets:
Neunkircher Str. 60
Executed by construction company:
Holzhandel Mietpark Woitke
Restriction:
Installation of a construction scaffold
Period:
10.06.2026 expected until 10.07.2026
Measure:
Work on a district heating pipeline
Streets:
Lasbachstraße near house number 22
Executed by construction company:
Baggerbetrieb Graber
Restriction:
Full road closure with corresponding detour
Period:
29.06.2026 expected until 10.07.2026
Measure:
Civil engineering work
Streets:
An der Hirtenwies 16
Executed by construction company:
Berila Bau GmbH
Restriction:
Sidewalk closure
Period:
23.06.2026 expected until 10.07.2026
Measure:
Work on the district heating pipeline
Streets:
Ahornweg as well as Ober den Stangen
Executed by construction company:
ENROTEC Versorgung GmbH & Co.KG
Restriction:
Sidewalk closure
Period:
01.07.2026 expected until 31.07.2026
Measure:
Sewer construction measure by GWQ
Streets:
Am Schwimmbad as well as the storage area In der Humes (parking lot closure)
Restriction:
Closure of parking spaces
Period:
expected until April 2027
The listing includes construction measures that were communicated to the administration in good time and before the deadline for acceptance in the Quierschieder Anzeiger. Short-term road excavations due to pipeline faults or emergency measures usually cannot be published in time. For inquiries regarding the construction measures, please contact the respective project sponsor. We ask for your understanding regarding the resulting traffic disruptions.